Demo complete ahead of schedule
The next step in the process is to finalize the preparation of 50,000+ square feet of concrete for pickleball court surfacing. The steel beam permits have been issued. The column removal and beam installation are scheduled to begin in early September. The fitness and golf areas continue to take shape – Professional golfer Dave Bisbee will be helping to create our tour quality, golf experience. Our Team continues to work on the fitness area design and finalizing of Espire’s membership program. The site plan permitting process at the City of Prescott is on schedule which will allow us to stay on the original timeline for a soft opening in January 2022. Also, we are in the final negotiation process with an exceptional Food and Beverage Partner to run our restaurant (The Kitchen) sports bar (name under review but open to your suggestions) and casual grill (The Volley). Please let us know if you have any questions, comments, or suggestions.
Thank you
Team Espire